Construction Schedule
April 13, 2007 10:09 AM
Project dates are estimated. Actual work events will vary, depending on various factors. Current schedules will be most accurate, based on weekly updates.
East-west traffic will be routed either to the northernmost two lanes or the southernmost two lanes of US-2 during construction.
PHASE 1 WORK ZONE: 22nd Ave. E to 7th Ave. E. (April - November 2007)
Box pipe storm sewer connect through 7th Ave. E. - Open Details
- 22nd Ave. E. Retention pond
- Bullhook Creek outfall
- Install box pipe across 22nd Street
- Build parking lot
- Remove asphalt on north side through 7th Ave. E
- Remove curb, gutter, sidewalk through 7th Ave. E
- Route traffic to south side through 7th Ave. E
- Storm pipe
- Storm mains 13th, 17th, 18th
Duration: 8-10 weeks
Dates: April-July 2007
|
Water utility 14th Ave. E - 7th Ave. E. - Open Details
- Gravel north side
- Remove asphalt from south side
- Remove curb, gutter, sidewalk
- Water mains
- Add service hook-ups
- Electrical
- Gravel south side
Duration: 6-8 weeks
Dates: July 17, 2007 - August 30, 2007
|
Resurface Phase 1 Work Zone - Open Details
- Portland Cement Concrete Paving left side with curb: 12 days
- Portland Cement Concrete Paving right side with curb: 12 days
- Retaining walls
- Sidewalks
- Signage
- Fencing
|
PHASE 2 WORK ZONE: 9th Ave. W. to 1st Ave. W. (July/Aug '07 - May '08)
Storm sewer and Grade improvements on West Ditch - Open Details
- Box pipe on Bullhook crossing
- Box pipe on West Ditch crossing
- Grade West Ditch
- Box pipe at 4th Ave. outfall
- Seed and mulch
Duration: 28 Days
Dates: July 23, 2007 - August 28, 2007
|
Excavation and utility work on northernmost lanes - Open Details
- Traffic to south
- Take up asphalt on north side
- Take up gutter, curbs, sidewalks on north side
- Install dewatering system
- Install sewer main
- Storm pipe and storm drain laterals
- MacDonald's storm pipe
- Gravel back up to street level
Dates: August 22, 2007 - November 8, 2007
|
Excavation and utility work on southernmost lanes - Open Details
- Traffic to north
- Take up asphalt on south side
- Remove curb and sidewalk
- Install water line
- Base rock both sides
- Gravel back up to street level
Duration: 12-13 weeks
Dates: March 10, 2008 - June 6, 2008
|
Resurface with concrete - Open Details
- Portland Cement Concrete Paving
- Curbs, Sidewalks
- Pave approaches
- Signage this section
Dates: April 16, 2008 - May 7, 2008
|
PHASE 3 WORK ZONE: 1st Ave. W. to 7th Ave. E. (March '07 - Oct/Nov '08)
North side excavation and utilities - Open Details
- Traffic moved to south lanes
- Remove asphalt from north lanes
- Remove curb, gutter, sidewalk
- Dewater soils
- Sanitary sewer installation
- Water line
- Water services
- Base rock north side
Dates: March 21, 2008 - June 3, 2008
|
Southside excavation and utilities - Open Details
- Move traffic to north
- Remove asphalt from south lanes
- Remove curb, gutter, sidewalk
- Storm main installation
- Base rock south side
- Electrical this section
Dates: June 3, 2008 - July 9, 2008
|
|
Havre Beneath the Streets
Dates: June 2008
|
Resurface this section - Open Details
- Portland Cement Concrete Paving
- Curbs
- Pedestrian Ramps
- Sidewalk
- Signage
- Landscaping
- Chipping
- Final striping
Dates: July 9, 2008 - September 4, 2008
|
|
|
Notify Me
Sign up here for automatic email updates about the construction schedule.
Information will also appear each Friday in the Havre Daily News.
Frequent updates will be heard on the following stations:
- KOJM 610 AM
- KRYK 101.3 FM
- KPQX 92.5 FM
Tune into local radio frequency 1610 AM for traffic advisories.
|