Construction Schedule

Project dates are estimated. Actual work events will vary, depending on various factors. Current schedules will be most accurate, based on weekly updates.

East-west traffic will be routed either to the northernmost two lanes or the southernmost two lanes of US-2 during construction.


PHASE 1 WORK ZONE: 22nd Ave. E to 7th Ave. E. (April - November 2007)
Box pipe storm sewer connect through 7th Ave. E. - Open Details
Duration: 8-10 weeks
Dates: April-July 2007
Water utility 14th Ave. E - 7th Ave. E. - Open Details
Duration: 6-8 weeks
Dates: July 17, 2007 - August 30, 2007
Resurface Phase 1 Work Zone - Open Details
PHASE 2 WORK ZONE: 9th Ave. W. to 1st Ave. W. (July/Aug '07 - May '08)
Storm sewer and Grade improvements on West Ditch - Open Details
Duration: 28 Days
Dates: July 23, 2007 - August 28, 2007
Excavation and utility work on northernmost lanes - Open Details
Dates: August 22, 2007 - November 8, 2007
Excavation and utility work on southernmost lanes - Open Details
Duration: 12-13 weeks
Dates: March 10, 2008 - June 6, 2008
Resurface with concrete - Open Details
Dates: April 16, 2008 - May 7, 2008
PHASE 3 WORK ZONE: 1st Ave. W. to 7th Ave. E. (March '07 - Oct/Nov '08)
North side excavation and utilities - Open Details
Dates: March 21, 2008 - June 3, 2008
Southside excavation and utilities - Open Details
Dates: June 3, 2008 - July 9, 2008
Havre Beneath the Streets
Dates: June 2008
Resurface this section - Open Details
Dates: July 9, 2008 - September 4, 2008

Notify Me

Sign up here for automatic email updates about the construction schedule. Information will also appear each Friday in the Havre Daily News.

Frequent updates will be heard on the following stations:

  • KOJM 610 AM
  • KRYK 101.3 FM
  • KPQX 92.5 FM

Tune into local radio frequency 1610 AM for traffic advisories.